Prompt: Arrival failures due to insufficient capacity

After the model has simulated the following prompt is displayed.

Simulation Complete, Do you want to see the results? (NOTE: There were entity arrival failures due to insufficient capacity)

Simulation Complete, Do you want to see the results? (NOTE: There were entity arrival failures due to insufficient capacity)

Reason:

Entity arrivals were scheduled to arrive. But because of limited capacity at the arrival location, they could not enter the model.

Solution:

Make sure you have a large enough capacity and/or input queue on the first activity following the arrival. Also make sure you haven’t assigned a shift to the activity that would cause the activity to be off shift when entities are scheduled to arrive.

Another way to avoid this message is to place a storage with sufficient capacity at the arrival location to act as a collection queue.

If you need further help, please contact support.

By |Comments Off on Prompt: Arrival failures due to insufficient capacity

About the Author:

Scott Baird has been president of ProcessModel for more than 15 years. His focus has been to teach others how to improve processes dramatically. He has been successful in transferring these skills to over 200 companies, including ESPN, NASA, GE, Nationwide, Cendant, SSA and many more. Specialties: Group facilitation for process improvement, process design and simulation, simulation modeling, business management and training others to see opportunities. Scott loves to teach process improvement and has often been heard to say, “Of all the things I do, training others to improve processes is my favorite.” Scott is a father of four and a grandfather of eight. He is an avid woodworker, designing and creating presentation boxes. In his spare time, he volunteers in a college preparation program.